3 photographs
White lighting of a bridge pier, 2018 > 2026
The Beynac bypass, in Dordogne, France, is a road project initiated in 1985. It consists of building a bypass road running alongside and above the Dordogne river. Since then, supporters and opponents have clashed.
On January 29, 2018, work on the bypass was authorized. What followed was a succession of protests, legal referrals, the annulment of the declaration of public utility, the suspension of work, appeals, rejections, a favorable opinion, annulment, a demolition order, penalties, an injunction to demolish, new penalties, a second bypass project, annulment, and river restoration work.
Started in January 2018, this work will end either with the completion or the disappearance of the bypass, or with a single bridge pier standing in the middle of the river. In 2026, the piers were demolished.
This bypass project cost the public more than 40 million euros.